The Magical Golf-Club Crans-sur-Sierre

As this season’s winter works draw to a close at, we reflect on what has been one of the more challenging and restrictive builds over the past few years. This season’s work has involved the following:

  • A new putting green, (twice the size of the previous one)
  • New tee complex for Hole 1,
  • Redesigned green complex for hole 2, as well as
  • A new green and tee complex for hole 3.

 

The actual scope of work itself was smaller in size and complexity to the previous season, however, an extremely wet late autumn meant that some of the main earthworks and drainage were unable to be completed, and would need to be finished off this spring. Which, considering the amount of the works, shouldn’t have been too much of an issue.

Then, along comes Covid-19, and the everything and everyone gets shaken to the core. The uncertainty of if, and when, works could recommence was unknown. Travel restrictions throughout Europe, hotels and restaurants all closed – it was all making things extremely difficult for both the Contractor and ourselves to get back to site.

 

Fortunately however, in the Canton the course is situated in, construction works were able to continue. And, thanks to client assistance in helping everyone obtain the necessary local and national authorizations for entry back into the country, we were all able to return safely to site.

Flights however, had been few and far between – some had to drive to different countries to catch a plane, some had to spend 24 hours in an airport. But, with one hotel still being open, and a restaurant able to deliver meals, at the beginning of April, works were able to tentatively get off the ground again.

 

Yes, works were slow initially, but as time went on and more of the workforce were able to get back into full swing, works progressed well, and we are now looking to be finished in the next two weeks. Considering all the challenges (and trying to get turf deliveries in from the UK), to only be a week or so behind schedule, is testament to all the hard work, dedication and commitment from the Client, the Contractors (SOL Golf and Arrosage Concept) and the head superintendent, Richard Barnes, and all his team. The changes are really starting to come together nicely, and, as the club continually aspire to keep getting better, this season’s work should prove to be another great step forward.

 

Reflecting back over the past 6 weeks, I do have to remind myself that this is Switzerland after all, and like a fine made Swiss watch, everything really does just work like clockwork.